Paragon Contractors LLC · Job 580 - South Elm Street Widening Phase II (W. 131st-121st), City of Jenks - Construction Sequence Schedule

Preliminary construction schedule per TCP Phases I/II/IIA/III/IIIA/IV (Plan Sheets 48-58) · read-only view
● LIVE working copy — reflects Schedule Chat edits · delivered packages stay on Project Views
Owner: City of JenksNTP: 6/15/26Planned Completion: 8/6/27Contract: 420 CDDeadline: 8/9/27
💬 Edit in Schedule Chat⬇ MS Project XMLOpen in MS Project (.mpp)Change log
IDActivityPhaseWDStartFinishJun '26Jul '26Aug '26Sep '26Oct '26Nov '26Dec '26Jan '27Feb '27Mar '27Apr '27May '27Jun '27Jul '27Aug '27
6/156/226/297/67/137/207/278/38/108/178/248/319/79/149/219/2810/510/1210/1910/2611/211/911/1611/2311/3012/712/1412/2112/281/41/111/181/252/12/82/152/223/13/83/153/223/294/54/124/194/265/35/105/175/245/316/76/146/216/287/57/127/197/268/28/9
PRECONSTRUCTION / GENERAL
1NTP — Notice to Proceed (ASSUMED 6/15/26 — reschedule project start when confirmed)Pre6/15/26
2Mobilization / Construction Staking PRELIMPre106/15/266/26/26
5Utility Clearance Verification — AT&T/ONG/P66/Explorer/Magellan/Enable/KM (CLEARED — AT&T last, actual 7/15/26)Pre236/15/267/15/26
3Signal & Median Power Procurement (LONG-LEAD — submittals + fabrication)Pre1956/22/263/19/27
4SWPPP / Silt Fence / Silt Dike Install (7,125 LF) PRELIMPre106/22/267/3/26
6TCP Phase I Setup + 48-hr Resident Notices PRELIMPre56/29/267/3/26
TCP PHASE I
7Clearing & Grubbing — Phase I Side PRELIMI307/6/268/14/26
8Removals — Pavement / C&G / Sidewalk / Sawing — Phase I Side (~4,600 SY) PRELIMI307/13/268/21/26
9Unclassified Excavation + Borrow — Phase I Side (~5,200 CY) PRELIMI407/20/269/11/26
10Waterline 'A' Relocation 6in PVC + Services — Creek Co RWD #2 (196 LF) PRELIMI307/27/269/4/26
11Storm Sewer Mainline & Laterals — Phase I Side (~4,150 LF) PRELIMI708/3/2611/6/26
12Inlets / Manholes / Junction Boxes — Phase I Side (~25 EA) PRELIMI708/10/2611/13/26
13Stabilized Subgrade (cement) — Phase I Side (~15,800 SY) PRELIMI309/14/2610/23/26
1412in Agg Base Type A + Separator Fabric — Phase I Side (~4,875 CY) PRELIMI309/21/2610/30/26
15Curb & Gutter — Phase I Side (~5,100 LF) PRELIMI309/28/2611/6/26
16Sidewalk / Trail / Driveways / ADA — Phase I Side PRELIMI3010/12/2611/20/26
178in Superpave S3 (2-3in lifts) + Temp Striping — Phase I Side (~4,450 TON) PRELIMI1510/19/2611/6/26
37Sodding / Restoration — Phase I Side (trailing) PRELIMI1510/26/2611/13/26
TCP PHASE II
18MILESTONE: Traffic Shift to Phase I Pavement / TCP Phase II SetupII11/9/26
19Removals + Excavation — Phase II Side (~5,200 CY) PRELIMII5011/9/261/15/27
20Double 6'x4' RCB — Exc / Form / Pour / Cure / CLSM Backfill (36 LF @ ~STA 19+50) PRELIMII3711/23/261/12/27
21Storm Sewer Mainline & Laterals — Phase II Side (~4,150 LF) PRELIMII7011/30/263/5/27
22Inlets / Manholes / Junction Boxes — Phase II Side (~25 EA) PRELIMII7012/7/263/12/27
23Stabilized Subgrade (cement) — Phase II Side (~15,800 SY) PRELIMII301/11/272/19/27
2412in Agg Base Type A + Separator Fabric — Phase II Side (~4,875 CY) PRELIMII301/18/272/26/27
25Curb & Gutter — Phase II Side (~5,100 LF) PRELIMII301/25/273/5/27
26Sidewalk / Trail / Driveways / ADA — Phase II Side PRELIMII302/8/273/19/27
278in Superpave S3 (2-3in lifts) — Phase II Side (~4,450 TON) PRELIMII152/15/273/5/27
38Sodding / Restoration — Phase II Side (trailing) PRELIMII153/1/273/19/27
TCP PHASE IIA
28Phase IIA — Intersection / Tie-in Zone (confirm scope, Plan Sheet 53)IIA153/1/273/19/27
TCP PHASE III
29MILESTONE: TCP Phase III Setup — Center ReconstructionIII3/22/27
30Cold Mill 3in + Fabric Reinforcement + 1in S6 Leveling (9,222 SY) PRELIMIII203/22/274/16/27
313in Superpave S4 Surface — Full Width (6,452 TON) PRELIMIII253/29/274/30/27
TCP PHASE IIIA
32Phase IIIA — Sub-zone (confirm scope, Plan Sheet 57)IIIA104/19/274/30/27
TCP PHASE IV
33Median Curb (8in special) + Landscaped Medians — 4 Ranges (4,140 LF) PRELIMIV305/3/276/11/27
34Median Power Install (Sheets 65-67) PRELIMIV205/10/276/4/27
35Traffic Signals Install (Sheets 5-6, 62-64) PRELIMIV255/10/276/11/27
39Sodding / Topsoil / Final Restoration (13,624 SY total job) PRELIMIV255/24/276/25/27
36Permanent Signing & Striping — Multi-polymer (~42,000 LF) PRELIMIV155/31/276/18/27
40Punchlist / Final Cleanup / Walkthrough PRELIMIV356/21/278/6/27
41MILESTONE: Substantial Completion (planned W56 — approx. 4 wks float vs 420 cd)IV8/6/27
Site / EarthworkUtility / StormConcreteAsphalt / PavingNEI / ElectricalRestoration / StripingMobilization / CloseoutTraffic ControlGate / HoldMilestoneMilestoneContract deadline week
Generated from the construction-schedule job-data model — kept in sync with the Excel grid and MS Project file. Durations flagged PRELIM / GATE are preliminary pending PM/superintendent input.