<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <Name>Job580_South_Elm_Widening_PhII</Name><Title>Job 580 - South Elm Street Widening Phase II (W. 131st-121st), City of Jenks - Construction Sequence Schedule</Title><Subject>Preliminary construction schedule per TCP Phases I/II/IIA/III/IIIA/IV (Plan Sheets 48-58)</Subject><Company>Paragon Contractors LLC</Company>
  <ScheduleFromStart>1</ScheduleFromStart><StartDate>2026-06-15T08:00:00</StartDate><CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime><DefaultFinishTime>17:00:00</DefaultFinishTime>
  <MinutesPerDay>480</MinutesPerDay><MinutesPerWeek>2400</MinutesPerWeek><DaysPerMonth>20</DaysPerMonth>
  <DefaultTaskType>0</DefaultTaskType><DurationFormat>7</DurationFormat><NewTasksEstimated>0</NewTasksEstimated><WeekStartDay>1</WeekStartDay><NewTasksAreManual>0</NewTasksAreManual>
  <ExtendedAttributes><ExtendedAttribute><FieldID>188743731</FieldID><FieldName>Text1</FieldName><Alias>Schedule Status</Alias></ExtendedAttribute></ExtendedAttributes>
  <Calendars><Calendar><UID>1</UID><Name>Standard</Name><IsBaseCalendar>1</IsBaseCalendar><BaseCalendarUID>-1</BaseCalendarUID><WeekDays><WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay><WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay></WeekDays></Calendar></Calendars>
  <Tasks>
    <Task><UID>0</UID><ID>0</ID><Name>Job580_South_Elm_Widening_PhII</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>0</OutlineNumber><OutlineLevel>0</OutlineLevel><Summary>1</Summary><Start>2026-06-15T08:00:00</Start><Finish>2027-08-06T17:00:00</Finish></Task>
    <Task><UID>9001</UID><ID>1</ID><Name>PRECONSTRUCTION / GENERAL</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-06-15T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish></Task>
    <Task><UID>1</UID><ID>2</ID><Name>NTP — Notice to Proceed (ASSUMED 6/15/26 — reschedule project start when confirmed)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-15T08:00:00</Start><Finish>2026-06-15T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>4</ConstraintType><ConstraintDate>2026-06-15T08:00:00</ConstraintDate><ExtendedAttribute><FieldID>188743731</FieldID><Value>CONFIRM — NTP date</Value></ExtendedAttribute><Notes>Placeholder NTP. To move whole schedule: Project &gt; Project Information &gt; Start date.</Notes></Task>
    <Task><UID>2</UID><ID>3</ID><Name>Mobilization / Construction Staking</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-15T08:00:00</Start><Finish>2026-06-26T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>1</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>3</UID><ID>4</ID><Name>Signal &amp; Median Power Procurement (LONG-LEAD — submittals + fabrication)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-22T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish><Duration>PT1560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>CONFIRM — long-lead w/ supplier</Value></ExtendedAttribute><Notes>Order at NTP. ~38-wk assumed lead — confirm with supplier; likely drives Phase IV start.</Notes><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>4</UID><ID>5</ID><Name>SWPPP / Silt Fence / Silt Dike Install (7,125 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-22T08:00:00</Start><Finish>2026-07-03T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>5</UID><ID>6</ID><Name>Utility Clearance Verification — AT&amp;T/ONG/P66/Explorer/Magellan/Enable/KM (CLEARED — AT&amp;T last, actual 7/15/26)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-15T08:00:00</Start><Finish>2026-07-15T17:00:00</Finish><Duration>PT184H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GREEN</Value></ExtendedAttribute><Notes>All 7 utilities verified clear. AT&amp;T final on 2026-07-15 (actual). Gate retired — duration set to reflect real clearance date.</Notes><PredecessorLink><PredecessorUID>1</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>6</UID><ID>7</ID><Name>TCP Phase I Setup + 48-hr Resident Notices</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-06-29T08:00:00</Start><Finish>2026-07-03T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Sheets 48-49; Note 13.</Notes><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9002</UID><ID>8</ID><Name>TCP PHASE I</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-07-06T08:00:00</Start><Finish>2026-11-20T17:00:00</Finish></Task>
    <Task><UID>7</UID><ID>9</ID><Name>Clearing &amp; Grubbing — Phase I Side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-07-06T08:00:00</Start><Finish>2026-08-14T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>6</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>8</UID><ID>10</ID><Name>Removals — Pavement / C&amp;G / Sidewalk / Sawing — Phase I Side (~4,600 SY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-07-13T08:00:00</Start><Finish>2026-08-21T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9</UID><ID>11</ID><Name>Unclassified Excavation + Borrow — Phase I Side (~5,200 CY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-07-20T08:00:00</Start><Finish>2026-09-11T17:00:00</Finish><Duration>PT320H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split</Value></ExtendedAttribute><Notes>High-PI corridor — 565 CO 003 precedent. Stabilization bid cement-only (no fly ash).</Notes><PredecessorLink><PredecessorUID>8</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>120000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>10</UID><ID>12</ID><Name>Waterline 'A' Relocation 6in PVC + Services — Creek Co RWD #2 (196 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-07-27T08:00:00</Start><Finish>2026-09-04T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>48-hr shutdown notices; valve ops and BAC-T by district = calendar holds inside this bar.</Notes><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>11</UID><ID>13</ID><Name>Storm Sewer Mainline &amp; Laterals — Phase I Side (~4,150 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-03T08:00:00</Start><Finish>2026-11-06T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (storm 6U1)</Value></ExtendedAttribute><Notes>Pipeline crossing risk zone — see gate task.</Notes><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>12</UID><ID>14</ID><Name>Inlets / Manholes / Junction Boxes — Phase I Side (~25 EA)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-10T08:00:00</Start><Finish>2026-11-13T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>11</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>13</UID><ID>15</ID><Name>Stabilized Subgrade (cement) — Phase I Side (~15,800 SY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-14T08:00:00</Start><Finish>2026-10-23T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (base 5B1)</Value></ExtendedAttribute><Notes>NO FLY ASH per General Note 19.</Notes><PredecessorLink><PredecessorUID>11</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>144000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>14</UID><ID>16</ID><Name>12in Agg Base Type A + Separator Fabric — Phase I Side (~4,875 CY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.8</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-21T08:00:00</Start><Finish>2026-10-30T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (base 5B1)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>13</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>15</UID><ID>17</ID><Name>Curb &amp; Gutter — Phase I Side (~5,100 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.9</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-28T08:00:00</Start><Finish>2026-11-06T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Monolithic doweled pours (Note 25).</Notes><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>16</UID><ID>18</ID><Name>Sidewalk / Trail / Driveways / ADA — Phase I Side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.10</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-12T08:00:00</Start><Finish>2026-11-20T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>15</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>17</UID><ID>19</ID><Name>8in Superpave S3 (2-3in lifts) + Temp Striping — Phase I Side (~4,450 TON)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.11</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-19T08:00:00</Start><Finish>2026-11-06T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (paving 6A1)</Value></ExtendedAttribute><Notes>This mat carries traffic during Phase II.</Notes><PredecessorLink><PredecessorUID>15</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>37</UID><ID>20</ID><Name>Sodding / Restoration — Phase I Side (trailing)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.12</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-26T08:00:00</Start><Finish>2026-11-13T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9003</UID><ID>21</ID><Name>TCP PHASE II</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-11-09T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish></Task>
    <Task><UID>18</UID><ID>22</ID><Name>MILESTONE: Traffic Shift to Phase I Pavement / TCP Phase II Setup</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-09T08:00:00</Start><Finish>2026-11-09T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>17</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>96000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>19</UID><ID>23</ID><Name>Removals + Excavation — Phase II Side (~5,200 CY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-09T08:00:00</Start><Finish>2027-01-15T17:00:00</Finish><Duration>PT400H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>20</UID><ID>24</ID><Name>Double 6'x4' RCB — Exc / Form / Pour / Cure / CLSM Backfill (36 LF @ ~STA 19+50)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-23T08:00:00</Start><Finish>2027-01-12T17:00:00</Finish><Duration>PT296H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>100 LF portable concrete barrier; Class AA 104 CY, reinf 18,133 LBS, CLSM 75 CY.</Notes><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>21</UID><ID>25</ID><Name>Storm Sewer Mainline &amp; Laterals — Phase II Side (~4,150 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-30T08:00:00</Start><Finish>2027-03-05T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (storm 6U1)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>22</UID><ID>26</ID><Name>Inlets / Manholes / Junction Boxes — Phase II Side (~25 EA)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-12-07T08:00:00</Start><Finish>2027-03-12T17:00:00</Finish><Duration>PT560H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>21</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>23</UID><ID>27</ID><Name>Stabilized Subgrade (cement) — Phase II Side (~15,800 SY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-01-11T08:00:00</Start><Finish>2027-02-19T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (base 5B1)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>21</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>144000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>168000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>24</UID><ID>28</ID><Name>12in Agg Base Type A + Separator Fabric — Phase II Side (~4,875 CY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-01-18T08:00:00</Start><Finish>2027-02-26T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (base 5B1)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>25</UID><ID>29</ID><Name>Curb &amp; Gutter — Phase II Side (~5,100 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.8</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-01-25T08:00:00</Start><Finish>2027-03-05T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>26</UID><ID>30</ID><Name>Sidewalk / Trail / Driveways / ADA — Phase II Side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.9</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-02-08T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>25</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>27</UID><ID>31</ID><Name>8in Superpave S3 (2-3in lifts) — Phase II Side (~4,450 TON)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.10</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-02-15T08:00:00</Start><Finish>2027-03-05T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (paving 6A1)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>25</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>38</UID><ID>32</ID><Name>Sodding / Restoration — Phase II Side (trailing)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.11</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-01T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9004</UID><ID>33</ID><Name>TCP PHASE IIA</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>4</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2027-03-01T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish></Task>
    <Task><UID>28</UID><ID>34</ID><Name>Phase IIA — Intersection / Tie-in Zone (confirm scope, Plan Sheet 53)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-01T08:00:00</Start><Finish>2027-03-19T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>CONFIRM — scope (Sht 53)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>27</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9005</UID><ID>35</ID><Name>TCP PHASE III</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>5</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2027-03-22T08:00:00</Start><Finish>2027-04-30T17:00:00</Finish></Task>
    <Task><UID>29</UID><ID>36</ID><Name>MILESTONE: TCP Phase III Setup — Center Reconstruction</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>5.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-22T08:00:00</Start><Finish>2027-03-22T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>28</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>30</UID><ID>37</ID><Name>Cold Mill 3in + Fabric Reinforcement + 1in S6 Leveling (9,222 SY)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>5.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-22T08:00:00</Start><Finish>2027-04-16T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (paving 6A1)</Value></ExtendedAttribute><Notes>ODOT 105.14: minimize mill-to-pave window; open milled sections at contractor risk.</Notes><PredecessorLink><PredecessorUID>29</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>31</UID><ID>38</ID><Name>3in Superpave S4 Surface — Full Width (6,452 TON)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>5.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-29T08:00:00</Start><Finish>2027-04-30T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — phase split (paving 6A1)</Value></ExtendedAttribute><Notes>Held tight behind milling by design.</Notes><PredecessorLink><PredecessorUID>30</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9006</UID><ID>39</ID><Name>TCP PHASE IIIA</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>6</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2027-04-19T08:00:00</Start><Finish>2027-04-30T17:00:00</Finish></Task>
    <Task><UID>32</UID><ID>40</ID><Name>Phase IIIA — Sub-zone (confirm scope, Plan Sheet 57)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>6.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-04-19T08:00:00</Start><Finish>2027-04-30T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>CONFIRM — scope (Sht 57)</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>31</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9007</UID><ID>41</ID><Name>TCP PHASE IV</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>7</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2027-05-03T08:00:00</Start><Finish>2027-08-06T17:00:00</Finish></Task>
    <Task><UID>33</UID><ID>42</ID><Name>Median Curb (8in special) + Landscaped Medians — 4 Ranges (4,140 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-03T08:00:00</Start><Finish>2027-06-11T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>STA 21+50, 32+48, 40+98, 48+98.</Notes><PredecessorLink><PredecessorUID>31</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>120000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>32</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>34</UID><ID>43</ID><Name>Median Power Install (Sheets 65-67)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-10T08:00:00</Start><Finish>2027-06-04T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>33</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>3</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>1104000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>35</UID><ID>44</ID><Name>Traffic Signals Install (Sheets 5-6, 62-64)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-10T08:00:00</Start><Finish>2027-06-11T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Material must be on hand from procurement task.</Notes><PredecessorLink><PredecessorUID>33</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>3</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>1104000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>36</UID><ID>45</ID><Name>Permanent Signing &amp; Striping — Multi-polymer (~42,000 LF)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-31T08:00:00</Start><Finish>2027-06-18T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>35</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>33</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>96000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>39</UID><ID>46</ID><Name>Sodding / Topsoil / Final Restoration (13,624 SY total job)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-24T08:00:00</Start><Finish>2027-06-25T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Season-constrained.</Notes><PredecessorLink><PredecessorUID>33</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>40</UID><ID>47</ID><Name>Punchlist / Final Cleanup / Walkthrough</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-06-21T08:00:00</Start><Finish>2027-08-06T17:00:00</Finish><Duration>PT280H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>36</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>72000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>41</UID><ID>48</ID><Name>MILESTONE: Substantial Completion (planned W56 — approx. 4 wks float vs 420 cd)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>7.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-08-06T08:00:00</Start><Finish>2027-08-06T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><Notes>Contract: 420 calendar days. Owner granted zero days across five COs on Phase I (Job 565) — protect float.</Notes><PredecessorLink><PredecessorUID>40</PredecessorUID><Type>0</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
  </Tasks>
</Project>