Change log — job 580

every Schedule Chat edit to job 580, newest first · back to the schedule view
When (UTC)WhoRequestChanges applied
2026-07-04 14:22yes, all utilities cleared
  • update uid 5 (Utility Clearance Verification — AT&T/ON): workdays 20→23, status "GATE — hard constraint"→"GREEN", name "GATE: Utility Clearance Verification — AT&T/ONG/P66/Explorer/Magellan/Enable/KM"→"Utility Clearance Verification — AT&T/ONG/P66/Explorer/Magellan/Enable/KM (CLEARED — AT&T last, actual 7/15/26)", notes undefined→"All 7 utilities verified clear. AT&T final on 2026-07-15 (actual). Gate retired — duration set to reflect real clearance date."
2026-07-04 13:52AT&T and the other utilities have cleared — close out the utility clearance gate as of 7/10 and confirm NTP is firm at 6/15. Also, the contractor wants clearing & grubbing Phase I padded by 5 more working days.
  • update uid 1 (NTP — Notice to Proceed (CONFIRMED 6/15/): name "NTP — Notice to Proceed (ASSUMED 6/15/26 — reschedule project start when confirmed)"→"NTP — Notice to Proceed (CONFIRMED 6/15/26)", status "CONFIRM — NTP date"→"MILESTONE", notes undefined→"NTP firm at 6/15/26."
  • update uid 5 (Utility Clearance Verification — AT&T/ON): name "GATE: Utility Clearance Verification — AT&T/ONG/P66/Explorer/Magellan/Enable/KM"→"Utility Clearance Verification — AT&T/ONG/P66/Explorer/Magellan/Enable/KM (CLEARED 7/10/26)", status "GATE — hard constraint"→"GREEN", notes undefined→"All utilities cleared as of 7/10/26. Gate closed out."
  • update uid 7 (Clearing & Grubbing — Phase I Side): workdays 30→35