P25-055-1 · Job 575 · South Grand Lake Regional Airport — Concrete Pour / Lot Plan
Crew sequence ① → ⑫ from the 10/14/26 markup · companion to the v5 schedule, data date 10/12/26 · planning exhibit, not a contract drawing
First pour: 11/03/26 (Alt 1 control strip)North complete: 02/11/27Mid complete: 03/08/27South / apron complete: 05/11/27One Ph 2B runway closure: 01/15–01/29/27 (NOTAM by 12/16)
Sheet 1 is the plan-oriented map (stations left to right, 3× vertical exaggeration). Sheet 2 is the pour table in crew order with the assumptions. Plan key sheets 1–4 put the same pours on the IFC plan sheets at true scale. Pinch or ctrl-scroll to zoom.Schedule (Gantt)Files (PIN)All schedules
Sheet 1 of 2 — map. Circled numbers are the crew's pour order; durations are the crew's; lot limits are planning splits to confirm against the joint plan.
Sheet 2 of 2 — pours in crew order with dates, and how the sequence was built.
Plan key 1 of 4 — SOUTH, Sta 100+00 → 118+00 at true scale, drawn from the IFC plan-sheet stations and edge offsets with the joint-plan panel grid. Brackets above = plan & profile sheets (5.x), below = joint plan sheets (7.x).
Plan key 2 of 4 — NORTH, Sta 116+00 → 134+00: Taxilane B, Taxiway A2, north lanes to the existing Taxiway A1 tie-in at 133+13.
Plan key 3 of 4 — cross-reference: pour → plan & profile sheet → joint plan sheet → stations → panel grid → SY → phase → dates → closure, plus how to read it against the plans and the apron question.
Plan key 4 of 4 — pour quantities and locations: schedule SY beside the plan-footprint SY (lanes only / with fillets), CY at 0.175 and trucks per pour, totals against the 23,490 SY contract.
Plan key sheets (added 10/16/26): the same twelve pours keyed to IFC plan set 17444-TO03 at true scale. Apron resolved 10/16 from joint plan 7.4 and sheet 5.0 read as drawings: three pieces of fill to the existing apron edge, about 2,275 SY; the 280-ft box the schedule rows carry does not exist, so pours ⑨–⑫ are re-cut with the crew before v6.
Dates come from the v5 schedule update (data date 10/12/26): one paving crew, pours back-to-back in the numbered order, weeks = 5 working days.
Items marked CONFIRM on the sheets are open questions for the team (sequential vs. overlapping crews, apron block limits and CO 002, holidays, the single 2B closure).
The live schedule is the Excel workbook; this page and the Gantt view are read-only snapshots of the same data.