P25-055-1 · Job 575 · South Grand Lake Regional Airport — Concrete Pour / Lot Plan

Crew sequence ① → ⑫ from the 10/14/26 markup · companion to the v5 schedule, data date 10/12/26 · planning exhibit, not a contract drawing
First pour: 11/03/26 (Alt 1 control strip)North complete: 02/11/27Mid complete: 03/08/27South / apron complete: 05/11/27One Ph 2B runway closure: 01/15–01/29/27 (NOTAM by 12/16)
Sheet 1 is the plan-oriented map (stations left to right, 3× vertical exaggeration). Sheet 2 is the pour table in crew order with the assumptions. Plan key sheets 1–4 put the same pours on the IFC plan sheets at true scale. Pinch or ctrl-scroll to zoom. Schedule (Gantt)Files (PIN)All schedules
Sheet 1 — pour / lot plan map: Taxiway A lanes, A2/A3/A4 connectors, Taxilanes B and C, and the apron blocks, numbered in the crew's pour order
Sheet 1 of 2 — map. Circled numbers are the crew's pour order; durations are the crew's; lot limits are planning splits to confirm against the joint plan.
Sheet 2 — pour table in crew order with dates, durations, and the assumptions behind the sequence
Sheet 2 of 2 — pours in crew order with dates, and how the sequence was built.
Plan key sheet 1 — south half (Sta 100+00 to 118+00) at true scale: Alt 1, Taxiway A4, south Taxiway A, apron blocks, Taxiway A3 and Taxilane C, with the plan and profile and joint plan sheet windows
Plan key 1 of 4 — SOUTH, Sta 100+00 → 118+00 at true scale, drawn from the IFC plan-sheet stations and edge offsets with the joint-plan panel grid. Brackets above = plan & profile sheets (5.x), below = joint plan sheets (7.x).
Plan key sheet 2 — north half (Sta 116+00 to 134+00) at true scale: Taxilane B, Taxiway A2 and the north Taxiway A lanes to the tie-in at 133+13
Plan key 2 of 4 — NORTH, Sta 116+00 → 134+00: Taxilane B, Taxiway A2, north lanes to the existing Taxiway A1 tie-in at 133+13.
Plan key sheet 3 — cross-reference table: each pour against its plan and profile sheet, joint plan sheet, stations, panel grid, square yards, CSPP phase, dates and closure
Plan key 3 of 4 — cross-reference: pour → plan & profile sheet → joint plan sheet → stations → panel grid → SY → phase → dates → closure, plus how to read it against the plans and the apron question.
Plan key sheet 4 — pour quantities and locations: schedule SY beside the plan-footprint SY, cubic yards and truck counts per pour, totals against the contract
Plan key 4 of 4 — pour quantities and locations: schedule SY beside the plan-footprint SY (lanes only / with fillets), CY at 0.175 and trucks per pour, totals against the 23,490 SY contract.