| Feb 2026 | Mar 2026 | Apr 2026 | May 2026 | Jun 2026 | Jul 2026 | Aug 2026 | Sep 2026 | Oct 2026 | Nov 2026 | Dec 2026 | Jan 2027 | Feb 2027 | Mar 2027 | Apr 2027 | May 2027 | Jun 2027 | Jul 2027 |
|---|
| WBS | ★ | ACTIVITY / TASK | PHASE | START | FINISH | CC | 02/16 | 02/23 | 03/02 | 03/09 | 03/16 | 03/23 | 03/30 | 04/06 | 04/13 | 04/20 | 04/27 | 05/04 | 05/11 | 05/18 | 05/25 | 06/01 | 06/08 | 06/15 | 06/22 | 06/29 | 07/06 | 07/13 | 07/20 | 07/27 | 08/03 | 08/10 | 08/17 | 08/24 | 08/31 | 09/07 | 09/14 | 09/21 | 09/28 | 10/05 | 10/12 | 10/19 | 10/26 | 11/02 | 11/09 | 11/16 | 11/23 | 11/30 | 12/07 | 12/14 | 12/21 | 12/28 | 01/04 | 01/11 | 01/18 | 01/25 | 02/01 | 02/08 | 02/15 | 02/22 | 03/01 | 03/08 | 03/15 | 03/22 | 03/29 | 04/05 | 04/12 | 04/19 | 04/26 | 05/03 | 05/10 | 05/17 | 05/24 | 05/31 | 06/07 | 06/14 | 06/21 | 06/28 | 07/05 | 07/12 | 07/19 | 07/26 |
|---|
| CALENDAR GATES — approved-plan closure windows + dated events (gates only, no work) |
| G1B | | ⏱ GATE — Ph 1B runway closure not before 04/01/26 (NOTAM by 03/02) | 1B | 02/16/26 | 03/31/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| GA1 | | ⏱ GATE — Alt 1 directed start 06/10/26 (Lochner 6/5 stop on Ph 1 → move to Alt 1; delay row D1) | Alt1 | 02/16/26 | 06/09/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| G2B | | ⏱ GATE — Ph 2B runway closure not before 06/25/26 (NOTAM by 05/26) | 2B | 02/16/26 | 06/24/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| G3 | | ⏱ GATE — Ph 3A earthwork not before 08/04/26 (approved-plan float) | 3A | 02/16/26 | 08/03/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| G2A | | ⏱ GATE — Mid-section earthwork actual start 06/01/26 (HJ unclassified excavation; CONFIRM) | 2A | 02/16/26 | 05/29/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| G3B | | ⏱ GATE — Ph 3B runway closure not before 09/03/26 (NOTAM by 08/04) | 3B | 02/16/26 | 09/02/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| GEL | | ⏱ GATE — TGE airfield electrical actual start 09/28/26 (Egis 9/22 / 10/6 minutes) | CL | 02/16/26 | 09/25/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| GRD | | ⏱ GATE — Paving-readiness items open from 10/12/26 (pre-pave meeting 10/13; data date) | 1A | 02/16/26 | 10/09/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| GPV | | ⏱ GATE — Paver (Manhattan) arrives 10/26/26 (pre-pave minutes 10/13 §5.A.v) | Alt1 | 02/16/26 | 10/23/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| MOBILIZATION & TEMPORARY CONTROLS |
| 1.1 | ★ | Mobilization / SPCD Submission | 1A | 02/16/26 | 02/20/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.2 | | Temp Barricades / Erosion Controls / CCCP | 1A | 02/23/26 | 02/27/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.3 | | One-Call Locate + Survey Lath at Limit Corners | 1A | 02/16/26 | 02/17/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PHASE 1A — NORTH SECTION (Runway OPEN ≤150d) | plan 02/16 → 03/31 · earthwork / drainage |
| 1.4 | ★ | Demo: Elec Systems / Storm Pipe / Pavement / Fence / C&G | 1A | 02/23/26 | 03/02/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.4.8 | ★ | Manhole R&R + Cleanout Modifications (LS) | 1A | 10/12/26 | 10/16/26 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.5 | ★ | Earthwork: Excav / Unsuitable R&R / Subbase / Agg Base (N 55%) | 1A | 03/02/26 | 10/14/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.6 | ★ | Drainage: Storm Pipe 15"/24"/30"/Arch + Underdrain — North | 1A | 03/09/26 | 10/16/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.6.3 | | Underdrain Cleanout Risers — North 7 EA | 1A | 10/19/26 | 10/19/26 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PHASE 1B — RSA CLOSURE NORTH (Runway CLOSED ≤14d) | plan 04/01 → 04/15 · structures |
| 1.7.1 | ★ | Install Closed RWY Markings + Low-Profile Barricades | 1B | 08/24/26 | 08/24/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.7.2 | ★ | DOUBLE 6'x3' RCB — 126 LF ★ CRITICAL STRUCTURE | 1B | 08/20/26 | 08/24/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.7.3 | ★ | RCB End Sections / Wing Walls (2 EA) + Concrete End Treatments (3 EA) | 1B | 08/31/26 | 10/16/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.7.5 | ★ | RCP End Sections: 15"/24"/30"/Arch (6 EA) | 1B | 08/28/26 | 08/31/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| ADD ALTERNATE NO. 1 — TAXIWAY A4 (Sta 200+00–202+63.55) + TW A Sta 100+00–107+17.85 (≤74 CD from start) | crew moved here 06/10/26 on Lochner direction |
| 4.1 | | Demolition + Earthwork — Alt 1 (Sta 100+00–107+00 + A4 connector Sta 200+00–202+25) | Alt1 | 06/10/26 | 10/02/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 4.3 | ★ | Storm Drainage + Underdrain + End Treatments — Alt 1 | Alt1 | 07/20/26 | 10/02/26 | 10 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PAVING READINESS — items the Egis pre-pave minutes (10/13/26) require BEFORE concrete | owners Clint / Elijah / GFAC / Eagle |
| RD.1 | ★ | Grade shots (P-209) + straightedge results — remaining areas Sta 107+00–121+00, A1/A2/A3 connectors → Egis review | 1A | 10/12/26 | 10/21/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.2 | ★ | QC Program (C-100 / ODOT 414-4.1) — corrections resubmittal (GFAC) | 1A | 10/12/26 | 10/16/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.3 | ★ | Class A concrete mix design — corrections resubmittal (Eagle Concrete) | 1A | 10/12/26 | 10/16/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.4 | | Lighting plan for early-morning / night paving (if used) — submit for RPR approval | 1A | 10/12/26 | 10/16/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.5 | ★ | Paving schedule + lot plan (joint plan with lots highlighted) — submit to Egis | 1A | 10/12/26 | 10/16/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.6 | ★ | Cold-weather paving plan (ODOT 414) — submit; November–January paving | 1A | 10/12/26 | 10/16/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| RD.7 | | Sanitary sewer encasement + Taxilane B manhole (Unified) ahead of the north pavement extension | 1A | 10/12/26 | 10/23/26 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PV.0 | ★ | Paver mobilization + setup (Manhattan paver/operator/mechanic; forms, 3 soft-cut saws, washout berms, haul route) | Alt1 | 10/26/26 | 11/02/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| EARTHWORK AHEAD OF THE PAVER — Mid + South/Apron base, drainage, removals | must be ready before pours ② and ③ |
| 2.1 | | Earthwork — Mid Section (~35% of total qtys): proof roll 113+00–118+00, geogrid, P-154, P-209 | 2A | 06/01/26 | 10/21/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.2 | ★ | Drainage: Storm Pipe + Underdrain — Mid Section | 2A | 09/28/26 | 10/14/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.5 | | Concrete End Treatments (2 EA) + Splash Pads (2 EA) | 2A | 10/15/26 | 10/15/26 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 3.1 | | Earthwork — South/Apron (~10% remaining) | 3A | 10/12/26 | 10/19/26 | 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 3.2 | ★ | Drainage: Final Storm Pipe + Underdrain + End Treatments | 3A | 10/12/26 | 10/16/26 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| CONCRETE PAVING — TEAM SEQUENCE ① → ⑫ (crew markup on the v4 pour plan, 10/14/26) | one paving crew, items run back-to-back · durations are the crew's (weeks = 5 wd) · stations per IFC sheets 5.0–5.9 / joint plans 7.0–7.7 |
| PA.1 | ★ | ★ ① CONTROL STRIP — Alt 1 Rt lane, TW A Sta 100+00→107+00 (700 LF × 17.5' ≈ 1,361 SY) — paving starts 11/3 | Alt1 | 11/03/26 | 11/03/26 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PA.2 | | ① Control-strip evaluation — QC/QA results, mix adjustment, Egis concurrence to proceed | Alt1 | 11/04/26 | 11/05/26 | 9 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PA.3 | | ① Alt 1 lanes — Lt lane fill-in Sta 100+00→107+17.85 + Rt lane 107+00→107+17.85 + fillets (≈1,430 SY) · crew: Alt 1 = 2 weeks from 11/3 | Alt1 | 11/06/26 | 11/16/26 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PN.1 | ★ | ② TW A lanes Sta 113+12→133+13 — Rt lane pilot + Lt lane fill-in, fillets, tie-in to existing Taxiway A1 (Mid + North as ONE paver run, ≈7,800 SY) · crew: 4 weeks | 1A | 11/17/26 | 12/14/26 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.1 | ★ | ③ South TW A lanes Sta 113+12→107+17.85 — both lanes incl. the 44.5' widened section 107+18–109+23 (≈2,300 SY) · crew: 1 week | 3A | 12/15/26 | 12/21/26 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PA.4 | | ④ Taxiway A4 connector OUTSIDE the RSA — Sta 200+17.5→202+26, both lanes + fillets (≈1,050 SY) · crew: 8 days | Alt1 | 12/22/26 | 12/31/26 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PM.3 | | ⑤ Taxiway A3 connector OUTSIDE the RSA — Sta 300+17.5→302+26, both lanes + fillets (≈1,100 SY) · crew: 2 weeks | 2A | 01/01/27 | 01/14/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PN.5 | | ⑥ Taxiway A2 connector OUTSIDE the RSA — Sta 400+17.5→402+26, both lanes + fillets (≈1,100 SY) · crew: 2 weeks | 1A | 01/15/27 | 01/28/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PN.5R | ★ | ★ A2 RSA END PANELS — Sta 402+26→402+63.2 + fillets (≈200 SY) — RUNWAY CLOSED (Ph 1B closure) | 1B | 01/29/27 | 01/29/27 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PN.7 | | ⑦ Taxilane B — Sta 600+17.5→601+82.2, both lanes + fillets (≈900 SY) · crew: 2 weeks | 1A | 01/29/27 | 02/11/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PM.1 | | ⑧ Taxilane C — Sta 500+17.5→501+82, both lanes + fillets (≈900 SY) · crew: 17 days | 2A | 02/12/27 | 03/08/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| P.1 | ★ | ★ Ph 1A/1B NORTH PAVEMENT COMPLETE (TW A north lanes + A2 + Taxilane B) — window closed 07/16/26, $—/CD running | 1A | 02/11/27 | 02/11/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | | | | | |
| P.2 | ★ | ★ Ph 2A MID PAVEMENT COMPLETE (TW A mid lanes + A3 + Taxilane C) — window closes 11/27/26 | 2A | 03/08/27 | 03/08/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | |
| PJ.1 | | Joint seal + ¼" bevel — Alt 1 + TW A lanes + connectors (Tri-City Seal; submittals pending) | 1A | 03/09/27 | 03/15/27 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.2 | | ⑨ Apron — east half of the bay nearest TW A (280' × 76.5' bay; ≈1,190 SY) · crew: 2 weeks | 3A | 03/09/27 | 03/22/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.3 | | ⑩ Apron — west half of the outer bay (280' × 44.5' bay; ≈690 SY) · crew: 8 days | 3A | 03/23/27 | 04/01/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.4 | | ⑪ Apron — east half of the outer bay (280' × 44.5' bay; ≈690 SY) · crew: 2 weeks | 3A | 04/02/27 | 04/15/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.5 | | ⑫ Apron — west half of the bay nearest TW A (280' × 76.5' bay; ≈1,190 SY) · crew: 8 days | 3A | 04/16/27 | 04/27/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PS.6 | | CO 002 / Amendment 1 added apron (plans 8/17: apron widened to 144.34' Lt at 107+18) + apron fill-ins / odd panels — SY CONFIRM · crew: 2 weeks | 3A | 04/28/27 | 05/11/27 | 4 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| P.3 | ★ | ★ Ph 3A SOUTH/APRON PAVEMENT COMPLETE (south lanes + apron + CO 002) — window closes 02/13/27 | 3A | 05/11/27 | 05/11/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | |
| PJ.2 | | Joint seal + bevel — taxilanes + South/Apron (Tri-City Seal) | 3A | 05/12/27 | 05/17/27 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PHASE 1B CLOSEOUT |
| 1.7.10 | ★ | ★ REOPEN Ph 1B (plan 04/15/26 · closure ≤14 CD) | 1B | 02/11/27 | 02/11/27 | 7 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | | | | | |
| 1.8 | ★ | 4x4 Grate Inlets (3 EA) + 4x4 Junction Box (1 EA) | 1A | 02/12/27 | 02/16/27 | 5 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PHASE 2B — RSA CLOSURE MID (Runway CLOSED ≤14d) | plan 06/25 → 07/09 |
| 2.7.1 | ★ | Install Closed RWY Markings | 2B | 01/15/27 | 01/15/27 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.7.2 | ★ | Earthwork + Drainage within RSA — Mid (start-to-finish, full closure window) | 2B | 01/18/27 | 01/29/27 | 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.7.3 | ★ | Pump Station Electrical Modifications (LS) | 2B | 01/18/27 | 01/20/27 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.7.5 | ★ | ★ A3 + A4 RSA END PANELS — Sta 302+26→302+63.3 and 202+26→202+63.55 + fillets (≈400 SY) — RUNWAY CLOSED | 2B | 01/18/27 | 01/19/27 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2.7.4 | ★ | ★ REOPEN Ph 2B (plan 07/09/26 · closure ≤14 CD) | 2B | 01/29/27 | 01/29/27 | 7 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | | | | | | | |
| P.A | ★ | ★ Alt 1 pavement complete (4,050 SY incl. A4 RSA end) — 72-hr cure before Alt 3 electrical | Alt1 | 01/19/27 | 01/19/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| MA1 | | ★ Add Alt 1 pavement complete (≤74 CD window from Alt 1 start) | Alt1 | 01/19/27 | 01/19/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| PHASE 3B — RSA CLOSURE SOUTH (Runway CLOSED ≤14d) | plan 09/03 → 09/17 |
| 3.6.1 | ★ | Install Closed RWY Markings | 3B | 05/12/27 | 05/12/27 | 2 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 3.6.2 | ★ | Earthwork + Drainage within RSA — South (start-to-finish, full closure window) | 3B | 05/13/27 | 05/26/27 | 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 3.6.3 | ★ | ★ FINAL REOPEN (plan 09/17/26 · closure ≤14 CD) | 3B | 05/26/27 | 05/26/27 | 7 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | | | | | | | |
| PROJECT CLOSEOUT | plan 09/18 → 12/14 |
| 5.1 | | Base Bid Electrical: Cables / Duct Bank / Handholes / Edge Light (TGE) | CL | 09/28/26 | 10/23/26 | 11 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.2 | | Alt 2 MITL — CCR / Edge Lights / Guidance Signs (Base Bid pave) | CL | 10/26/26 | 11/04/26 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.3 | | Alt 3 MITL — Lights + Signs (Alt 1 pavement) | Alt1 | 01/20/27 | 01/27/27 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.4 | | Pavement Markings — All Sections (permanent) + hold bars before opening to aircraft | CL | 05/18/27 | 05/24/27 | 6 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.5 | ★ | Seeding / Sodding / Mulching — All Disturbed Areas | CL | 05/25/27 | 06/04/27 | 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.6 | | Grass establishment period (engineer confirmation) | CL | 06/07/27 | 07/08/27 | 1 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 5.7 | ★ | ★ GRASS STAND CONFIRMED BY ENGINEER (plan 12/11/26) | — | 07/09/27 | 07/09/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | | |
| 5.8 | ★ | ★ SUBSTANTIAL COMPLETION (plan 12/14/26 · CONTRACT 02/27/27) | — | 07/12/27 | 07/12/27 | 8 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | ◆ | | |