P25-055-1 · JOB 575 · SOUTH GRAND LAKE REGIONAL AIRPORT · CSPP CONSTRUCTION SCHEDULE · AC 150/5370-2G · DELAY & TIME-EXTENSION SCHEDULE · CONCRETE PAVING IN THE CREW'S SEQUENCE ① → ⑫ (10/14/26 markup) (376 CD · phase windows with $—/CD LDs each)

NTP: 02/16/26Data date: 10/12/26Contract completion: 02/27/27 (376 CD)P.1 cap 150 CD: 02/11/27 (360 CD, float -150 wd)1.7.10 cap 164 CD: 02/11/27 (360 CD, float -140 wd)P.2 cap 284 CD: 03/08/27 (385 CD, float -71 wd)2.7.4 cap 302 CD: 01/29/27 (347 CD, float -33 wd)P.3 cap 362 CD: 05/11/27 (449 CD, float -62 wd)3.6.3 cap 376 CD: 05/26/27 (464 CD, float -63 wd)5.8 cap 376 CD: 07/12/27 (511 CD, float -96 wd)MA1 cap 74 CD: 01/19/27 (223 CD, float -107 wd)2.7.4 cap 18 CD: 01/29/27 (14 CD, float 2 wd)3.6.3 cap 14 CD: 05/26/27 (14 CD, float 0 wd)Forecast SC: 07/12/27
Read-only web view — the live schedule is the Excel workbook (green cells, Ctrl+Alt+F9). Generated 10/14/2026 from the 10/12/2026 update. Pour / lot plan (crew sequence) Files (PIN) All schedules
Feb 2026Mar 2026Apr 2026May 2026Jun 2026Jul 2026Aug 2026Sep 2026Oct 2026Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027Apr 2027May 2027Jun 2027Jul 2027
WBS★ACTIVITY / TASKPHASESTARTFINISHCC02/1602/2303/0203/0903/1603/2303/3004/0604/1304/2004/2705/0405/1105/1805/2506/0106/0806/1506/2206/2907/0607/1307/2007/2708/0308/1008/1708/2408/3109/0709/1409/2109/2810/0510/1210/1910/2611/0211/0911/1611/2311/3012/0712/1412/2112/2801/0401/1101/1801/2502/0102/0802/1502/2203/0103/0803/1503/2203/2904/0504/1204/1904/2605/0305/1005/1705/2405/3106/0706/1406/2106/2807/0507/1207/1907/26
CALENDAR GATES — approved-plan closure windows + dated events (gates only, no work)
G1B⏱ GATE — Ph 1B runway closure not before 04/01/26 (NOTAM by 03/02)1B02/16/2603/31/2610
GA1⏱ GATE — Alt 1 directed start 06/10/26 (Lochner 6/5 stop on Ph 1 → move to Alt 1; delay row D1)Alt102/16/2606/09/2610
G2B⏱ GATE — Ph 2B runway closure not before 06/25/26 (NOTAM by 05/26)2B02/16/2606/24/2610
G3⏱ GATE — Ph 3A earthwork not before 08/04/26 (approved-plan float)3A02/16/2608/03/2610
G2A⏱ GATE — Mid-section earthwork actual start 06/01/26 (HJ unclassified excavation; CONFIRM)2A02/16/2605/29/2610
G3B⏱ GATE — Ph 3B runway closure not before 09/03/26 (NOTAM by 08/04)3B02/16/2609/02/2610
GEL⏱ GATE — TGE airfield electrical actual start 09/28/26 (Egis 9/22 / 10/6 minutes)CL02/16/2609/25/2610
GRD⏱ GATE — Paving-readiness items open from 10/12/26 (pre-pave meeting 10/13; data date)1A02/16/2610/09/2610
GPV⏱ GATE — Paver (Manhattan) arrives 10/26/26 (pre-pave minutes 10/13 §5.A.v)Alt102/16/2610/23/2611
MOBILIZATION & TEMPORARY CONTROLS
1.1★Mobilization / SPCD Submission1A02/16/2602/20/2610
1.2Temp Barricades / Erosion Controls / CCCP1A02/23/2602/27/2610
1.3One-Call Locate + Survey Lath at Limit Corners1A02/16/2602/17/2610
PHASE 1A — NORTH SECTION (Runway OPEN ≤150d) | plan 02/16 → 03/31 · earthwork / drainage
1.4★Demo: Elec Systems / Storm Pipe / Pavement / Fence / C&G1A02/23/2603/02/2610
1.4.8★Manhole R&R + Cleanout Modifications (LS)1A10/12/2610/16/265
1.5★Earthwork: Excav / Unsuitable R&R / Subbase / Agg Base (N 55%)1A03/02/2610/14/2611
1.6★Drainage: Storm Pipe 15"/24"/30"/Arch + Underdrain — North1A03/09/2610/16/2611
1.6.3Underdrain Cleanout Risers — North 7 EA1A10/19/2610/19/265
PHASE 1B — RSA CLOSURE NORTH (Runway CLOSED ≤14d) | plan 04/01 → 04/15 · structures
1.7.1★Install Closed RWY Markings + Low-Profile Barricades1B08/24/2608/24/2610
1.7.2★DOUBLE 6'x3' RCB — 126 LF ★ CRITICAL STRUCTURE1B08/20/2608/24/2610
1.7.3★RCB End Sections / Wing Walls (2 EA) + Concrete End Treatments (3 EA)1B08/31/2610/16/2611
1.7.5★RCP End Sections: 15"/24"/30"/Arch (6 EA)1B08/28/2608/31/2610
ADD ALTERNATE NO. 1 — TAXIWAY A4 (Sta 200+00–202+63.55) + TW A Sta 100+00–107+17.85 (≤74 CD from start) | crew moved here 06/10/26 on Lochner direction
4.1Demolition + Earthwork — Alt 1 (Sta 100+00–107+00 + A4 connector Sta 200+00–202+25)Alt106/10/2610/02/2610
4.3★Storm Drainage + Underdrain + End Treatments — Alt 1Alt107/20/2610/02/2610
PAVING READINESS — items the Egis pre-pave minutes (10/13/26) require BEFORE concrete | owners Clint / Elijah / GFAC / Eagle
RD.1★Grade shots (P-209) + straightedge results — remaining areas Sta 107+00–121+00, A1/A2/A3 connectors → Egis review1A10/12/2610/21/269
RD.2★QC Program (C-100 / ODOT 414-4.1) — corrections resubmittal (GFAC)1A10/12/2610/16/269
RD.3★Class A concrete mix design — corrections resubmittal (Eagle Concrete)1A10/12/2610/16/269
RD.4Lighting plan for early-morning / night paving (if used) — submit for RPR approval1A10/12/2610/16/269
RD.5★Paving schedule + lot plan (joint plan with lots highlighted) — submit to Egis1A10/12/2610/16/269
RD.6★Cold-weather paving plan (ODOT 414) — submit; November–January paving1A10/12/2610/16/269
RD.7Sanitary sewer encasement + Taxilane B manhole (Unified) ahead of the north pavement extension1A10/12/2610/23/265
PV.0★Paver mobilization + setup (Manhattan paver/operator/mechanic; forms, 3 soft-cut saws, washout berms, haul route)Alt110/26/2611/02/269
EARTHWORK AHEAD OF THE PAVER — Mid + South/Apron base, drainage, removals | must be ready before pours ② and ③
2.1Earthwork — Mid Section (~35% of total qtys): proof roll 113+00–118+00, geogrid, P-154, P-2092A06/01/2610/21/2611
2.2★Drainage: Storm Pipe + Underdrain — Mid Section2A09/28/2610/14/2611
2.5Concrete End Treatments (2 EA) + Splash Pads (2 EA)2A10/15/2610/15/265
3.1Earthwork — South/Apron (~10% remaining)3A10/12/2610/19/261
3.2★Drainage: Final Storm Pipe + Underdrain + End Treatments3A10/12/2610/16/265
CONCRETE PAVING — TEAM SEQUENCE ① → ⑫ (crew markup on the v4 pour plan, 10/14/26) | one paving crew, items run back-to-back · durations are the crew's (weeks = 5 wd) · stations per IFC sheets 5.0–5.9 / joint plans 7.0–7.7
PA.1★★ ① CONTROL STRIP — Alt 1 Rt lane, TW A Sta 100+00→107+00 (700 LF × 17.5' ≈ 1,361 SY) — paving starts 11/3Alt111/03/2611/03/264
PA.2① Control-strip evaluation — QC/QA results, mix adjustment, Egis concurrence to proceedAlt111/04/2611/05/269
PA.3① Alt 1 lanes — Lt lane fill-in Sta 100+00→107+17.85 + Rt lane 107+00→107+17.85 + fillets (≈1,430 SY) · crew: Alt 1 = 2 weeks from 11/3Alt111/06/2611/16/264
PN.1★② TW A lanes Sta 113+12→133+13 — Rt lane pilot + Lt lane fill-in, fillets, tie-in to existing Taxiway A1 (Mid + North as ONE paver run, ≈7,800 SY) · crew: 4 weeks1A11/17/2612/14/264
PS.1★③ South TW A lanes Sta 113+12→107+17.85 — both lanes incl. the 44.5' widened section 107+18–109+23 (≈2,300 SY) · crew: 1 week3A12/15/2612/21/264
PA.4④ Taxiway A4 connector OUTSIDE the RSA — Sta 200+17.5→202+26, both lanes + fillets (≈1,050 SY) · crew: 8 daysAlt112/22/2612/31/264
PM.3⑤ Taxiway A3 connector OUTSIDE the RSA — Sta 300+17.5→302+26, both lanes + fillets (≈1,100 SY) · crew: 2 weeks2A01/01/2701/14/274
PN.5⑥ Taxiway A2 connector OUTSIDE the RSA — Sta 400+17.5→402+26, both lanes + fillets (≈1,100 SY) · crew: 2 weeks1A01/15/2701/28/274
PN.5R★★ A2 RSA END PANELS — Sta 402+26→402+63.2 + fillets (≈200 SY) — RUNWAY CLOSED (Ph 1B closure)1B01/29/2701/29/272
PN.7⑦ Taxilane B — Sta 600+17.5→601+82.2, both lanes + fillets (≈900 SY) · crew: 2 weeks1A01/29/2702/11/274
PM.1⑧ Taxilane C — Sta 500+17.5→501+82, both lanes + fillets (≈900 SY) · crew: 17 days2A02/12/2703/08/274
P.1★★ Ph 1A/1B NORTH PAVEMENT COMPLETE (TW A north lanes + A2 + Taxilane B) — window closed 07/16/26, $—/CD running1A02/11/2702/11/278◆
P.2★★ Ph 2A MID PAVEMENT COMPLETE (TW A mid lanes + A3 + Taxilane C) — window closes 11/27/262A03/08/2703/08/278◆
PJ.1Joint seal + ¼" bevel — Alt 1 + TW A lanes + connectors (Tri-City Seal; submittals pending)1A03/09/2703/15/276
PS.2⑨ Apron — east half of the bay nearest TW A (280' × 76.5' bay; ≈1,190 SY) · crew: 2 weeks3A03/09/2703/22/274
PS.3⑩ Apron — west half of the outer bay (280' × 44.5' bay; ≈690 SY) · crew: 8 days3A03/23/2704/01/274
PS.4⑪ Apron — east half of the outer bay (280' × 44.5' bay; ≈690 SY) · crew: 2 weeks3A04/02/2704/15/274
PS.5⑫ Apron — west half of the bay nearest TW A (280' × 76.5' bay; ≈1,190 SY) · crew: 8 days3A04/16/2704/27/274
PS.6CO 002 / Amendment 1 added apron (plans 8/17: apron widened to 144.34' Lt at 107+18) + apron fill-ins / odd panels — SY CONFIRM · crew: 2 weeks3A04/28/2705/11/274
P.3★★ Ph 3A SOUTH/APRON PAVEMENT COMPLETE (south lanes + apron + CO 002) — window closes 02/13/273A05/11/2705/11/278◆
PJ.2Joint seal + bevel — taxilanes + South/Apron (Tri-City Seal)3A05/12/2705/17/276
PHASE 1B CLOSEOUT
1.7.10★★ REOPEN Ph 1B (plan 04/15/26 · closure ≤14 CD)1B02/11/2702/11/277◆
1.8★4x4 Grate Inlets (3 EA) + 4x4 Junction Box (1 EA)1A02/12/2702/16/275
PHASE 2B — RSA CLOSURE MID (Runway CLOSED ≤14d) | plan 06/25 → 07/09
2.7.1★Install Closed RWY Markings2B01/15/2701/15/272
2.7.2★Earthwork + Drainage within RSA — Mid (start-to-finish, full closure window)2B01/18/2701/29/271
2.7.3★Pump Station Electrical Modifications (LS)2B01/18/2701/20/276
2.7.5★★ A3 + A4 RSA END PANELS — Sta 302+26→302+63.3 and 202+26→202+63.55 + fillets (≈400 SY) — RUNWAY CLOSED2B01/18/2701/19/272
2.7.4★★ REOPEN Ph 2B (plan 07/09/26 · closure ≤14 CD)2B01/29/2701/29/277◆
P.A★★ Alt 1 pavement complete (4,050 SY incl. A4 RSA end) — 72-hr cure before Alt 3 electricalAlt101/19/2701/19/278◆
MA1★ Add Alt 1 pavement complete (≤74 CD window from Alt 1 start)Alt101/19/2701/19/278◆
PHASE 3B — RSA CLOSURE SOUTH (Runway CLOSED ≤14d) | plan 09/03 → 09/17
3.6.1★Install Closed RWY Markings3B05/12/2705/12/272
3.6.2★Earthwork + Drainage within RSA — South (start-to-finish, full closure window)3B05/13/2705/26/271
3.6.3★★ FINAL REOPEN (plan 09/17/26 · closure ≤14 CD)3B05/26/2705/26/277◆
PROJECT CLOSEOUT | plan 09/18 → 12/14
5.1Base Bid Electrical: Cables / Duct Bank / Handholes / Edge Light (TGE)CL09/28/2610/23/2611
5.2Alt 2 MITL — CCR / Edge Lights / Guidance Signs (Base Bid pave)CL10/26/2611/04/266
5.3Alt 3 MITL — Lights + Signs (Alt 1 pavement)Alt101/20/2701/27/276
5.4Pavement Markings — All Sections (permanent) + hold bars before opening to aircraftCL05/18/2705/24/276
5.5★Seeding / Sodding / Mulching — All Disturbed AreasCL05/25/2706/04/271
5.6Grass establishment period (engineer confirmation)CL06/07/2707/08/271
5.7★★ GRASS STAND CONFIRMED BY ENGINEER (plan 12/11/26)—07/09/2707/09/278◆
5.8★★ SUBSTANTIAL COMPLETION (plan 12/14/26 · CONTRACT 02/27/27)—07/12/2707/12/278◆

Compliance calendar — advance notices

DUE BYNOTICELEADNOTES
07/25/26 PAST DUENOTAM — Ph 1B runway closure (RSA North)30 CD before 1.7.1 (08/24/26)Approved CSPP deadline 03/02/2026
10/27/26Notify RPR one week before the paving phase starts (CSPP 1.7 NOTAMs)7 CD before PA.1 (11/03/26)Contractor notifies the RPR ≥1 week before each phase so the Airport Manager can issue NOTAMs
11/01/2648-hr notice to Egis inspector — first concrete pour (QA testing)2 CD before PA.1 (11/03/26)Progress minutes 9/22 & 10/6: notify Egis 48 hours before each pour; repeats for every pour
12/16/26NOTAM — Ph 2B runway closure (RSA Mid)30 CD before 2.7.1 (01/15/27)Approved CSPP deadline 05/26/2026
12/30/26NOTAM — Ph 1B runway closure for the A2 RSA end panels30 CD before PN.5R (01/29/27)CSPP 1.7: 30 days for a Runway 18-36 closure; airport operator issues; notify RPR 1 week before the phase
04/12/27NOTAM — Ph 3B runway closure (RSA South)30 CD before 3.6.1 (05/12/27)Approved CSPP deadline 08/04/2026

Legend — CC color codes

Earthwork / grading / aggregate / subbaseTemp marking, barricades, closed-areaAdd Alt No.1 — RSA gradingAsphalt paving (mill / overlay / surface)Structures & drainageElectrical / lighting / pavement markingsOPEN / reopen milestoneSubstantial completion / final acceptanceFAA compliance / coordinationActual — completeIn progress

Notes

• BASELINE = approved CSPP schedule (P250551_SGLRA_CSPP_Schedule.xlsx, NTP 02/16/26, planned completion 12/14/26) — reproduced in v3. CONTRACT TIME = 376 CD → 02/27/27 (NTP; Lochner minutes). GP-36 phase windows run back-to-back, each with $—/CD LDs: 1A 150 (to 7/16) · 1B 14 (7/30) · 2A 120 (11/27) · 2B 18 (12/15) · 3A 60 (2/13/27) · 3B 14 (2/27/27). Art. 29 adds $—/CD on overall completion.
• CONCRETE STAGING (Egis pre-pave minutes 10/13/26): paver on site 10/26, paving starts 11/3 with the control strip (700 LF × 17.5', Sta 100+00–107+00, Alt 1); production ≈ 800 LF × 17.5' ≈ 1,500 SY/day; lots = 2,500 SY or one day's production; Eagle Concrete 8–10 trucks, ~80 CY/hr, 17-min haul; wood fixed forms + roller screed; fill-in lanes / any traffic on a slab only after 3,100 psi (dowel drilling after 7 days or 3,100 psi); 48-hr notice to Egis before every pour; no concrete on frost, mix 50–90°F, cold-weather plan required; concrete paid at 75% until 28-day breaks, pay factors applied, joints beveled and sealed; hold bars painted before opening to aircraft.
• Pour rows are 2 working days each (forms/dowel baskets, then the pour) at one lane-day ≈ 1,500 SY. Geometry from the IFC plans (17444-TO03): TW A base bid Sta 107+17.85–133+13, 35' wide (two 17.5' lanes, 8.75' panels); A3 at 113+82, A2 at 131+41, Taxilanes C/B at 114+75 / 117+80; Alt 1 = TW A 100+00–107+17.85 + A4 at 100+17.5. Phase limits per sheet 1.6: 1A north of Taxilane B · 2A Taxilane B down to the apron · 3A apron + remaining TW A · B-phases = the RSA (75' from runway CL) under a runway closure. Section quantities from that geometry (North ≈8,200 · Mid ≈4,000 · South/Apron ≈4,600 · Alt 1 4,050 = 17,550 + 4,050 SY); the approved schedule's 9,675/6,143/1,733 split was an estimate. CO 002 added apron is NOT in the 17,550 SY (CONFIRM SY).
• CSPP CONSTRAINTS (AC 150/5370-2G §4): Ph 1B / 2B / 3B RSA closures ≤14 CD each · 30-day NOTAM before each closure · Runway OPEN during A-phases · Alt 1 ≤74 CD from its start.
• DELAYS & TIME EXTENSIONS section (red) is the record. GP 80-07.1: weather days are INCLUDED in contract time (no weather extension — logged here as record only); only calendar days between the Owner's WRITTEN orders to suspend and resume work are excluded; contract time is also increased at final payment in proportion to actual vs estimated quantity cost (CO'd work excluded). Only executed modifications count as granted.
• WRITTEN RECORD behind the owner-direction rows: Lochner progress minutes 5/19, 6/2, 6/16, 6/30, 7/14, 7/28, 8/11, 8/25, 9/8; Egis minutes 9/22, 10/6; Ignacio e-mails 6/15, 6/18, 7/14 (rock placement on hold), 7/22, 8/3, 8/5 (directive), 8/12 (unsuitable bid item used), 8/26; Kirk Evans 7/15 directive; Egis 9/9 fill approval; Tyler letters 5/29, 6/18, 8/3, 8/11 — all in Tyler's Outlook 'Job 575' folder and P:\Correspondence.
• Bars auto-update: edit the green NTP cell or any green DUR (working-days) cell, then press Ctrl+Alt+F9 to recalc. Durations are working days; contract caps are calendar days.