Paragon Contractors LLC · Job 584 — PRY Marcus WWTP Expansion (Google Pryor MARCUS) — BP 31.01 Earthwork & Utilities

Paragon subcontract SC-8864-010 under Manhattan Construction — FIRST PASS (durations PRELIM; reconcile vs Manhattan P6) · read-only view
● LIVE working copy — reflects Schedule Chat edits · last updated 2026-07-17 19:15 UTC · delivered packages stay on Project Views
Owner: Manhattan Construction / Google (DCS MARCUS)NTP: 8/2/26Planned Completion: 6/22/27Contract: 420 CDDeadline: 9/26/27
💬 Edit in Schedule Chat⬇ MS Project XMLOpen in MS Project (.mpp)Change log
IDActivityPhaseWDStartFinishJul '26Aug '26Sep '26Oct '26Nov '26Dec '26Jan '27Feb '27Mar '27Apr '27May '27Jun '27Jul '27Aug '27Sep '27
7/278/38/108/178/248/319/79/149/219/2810/510/1210/1910/2611/211/911/1611/2311/3012/712/1412/2112/281/41/111/181/252/12/82/152/223/13/83/153/223/294/54/124/194/265/35/105/175/245/316/76/146/216/287/57/127/197/268/28/98/168/238/309/69/139/20
PRECONSTRUCTION / SITE-WIDE
1★ NTP / Notice to ProceedPre8/3/26
2Mobilization / site setup / GC crew (60-wk general conditions)Pre58/3/268/7/26
3Submittals / MOPs / shop drawings — initial package PRELIMPre158/3/268/21/26
4Silt fence perimeter + stabilized construction entrances PRELIMPre88/6/268/17/26
5GPR + hydro-excavation utility locates (site-wide) GATEPre108/6/268/19/26
6Re-route process water piping — KEEP TANKS LIVE GATEPre108/20/269/2/26
7Demolition — storm piping/structures, concrete, Valve Group 6 slab + enclosure R&R PRELIMPre159/3/269/23/26
EQUALIZATION TANK SIDE — CREW 1
8Clear / strip / stockpile topsoil — EQ side PRELIMEQ89/10/269/21/26
9Mass excavation — EQ tank pad + pump house PRELIMEQ209/22/2610/19/26
10Engineered / select fill — EQ pad (to 5 ft outside perimeter) PRELIMEQ1510/6/2610/26/26
11★ EQ tank pad ready for tank contractorEQ10/27/26
12EQ tank erection window — BY OTHERS (BP 40.01) GATEEQ10010/27/263/15/27
13Yard piping — EQ side: DI wastewater + storm sewer + structures (~250 LF 8", 12"/24" runs, 18" RCP) PRELIMEQ3011/24/261/4/27
14Process piping tie-ins — EQ tank (16" connector + P-lines) PRELIMEQ203/16/274/12/27
15Backfill / return to grade / gravel access road — EQ side (10 ft around tank) PRELIMEQ104/13/274/26/27
24-HR HOLDING TANK SIDE — CREW 2
16Clear / strip / stockpile topsoil — 24-hr tank side PRELIMHT89/10/269/21/26
17Mass excavation — 24-hr holding tank pad PRELIMHT209/22/2610/19/26
18Engineered / select fill — 24-hr tank pad PRELIMHT1510/6/2610/26/26
19★ 24-hr tank pad ready for tank contractorHT10/27/26
2024-hr tank erection window — BY OTHERS (BP 40.01) GATEHT10010/27/263/15/27
21Yard piping — HT side: transfer piping (12" MegaCub) + 8" effluent + storm PRELIMHT3011/24/261/4/27
22Process piping tie-ins — 24-hr tank PRELIMHT203/16/274/12/27
23Backfill / return to grade / gravel access road — HT side PRELIMHT104/13/274/26/27
COMMISSIONING / CLOSEOUT
27QA/QC testing + documentation (plans 2 wks ahead of testing) PRELIMCL103/16/273/29/27
24Aggregate base + fine-grade subgrade for paving (asphalt BY OTHERS) PRELIMCL154/27/275/17/27
25Structure lid adjustments + valve tagging / tracer wire / labeling PRELIMCL54/27/275/3/27
28Commissioning — L1/L2/L3 (+ L4/L5 support) GATECL155/4/275/24/27
26Site restoration / topsoil / vegetation + erosion-control removal PRELIMCL105/18/275/31/27
29Closeout documentation — MARCUS Deliverables Matrix + as-builts PRELIMCL106/1/276/14/27
30★ SUBSTANTIAL COMPLETIONCL6/15/27
31★ FINAL COMPLETION / DEMOBCL6/22/27
Site / EarthworkUtility / StormRestoration / StripingMobilization / CloseoutGate / HoldMilestoneMilestoneContract deadline week