<Project xmlns="http://schemas.microsoft.com/project">
  <Name>584 PRY Marcus WWTP Expansion</Name><Title>Job 584 — PRY Marcus WWTP Expansion (Google Pryor MARCUS) — BP 31.01 Earthwork &amp; Utilities</Title><Subject>Paragon subcontract SC-8864-010 under Manhattan Construction — FIRST PASS (durations PRELIM; reconcile vs Manhattan P6)</Subject><Company>Paragon Contractors LLC</Company>
  <ScheduleFromStart>1</ScheduleFromStart><StartDate>2026-08-02T08:00:00</StartDate><CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime><DefaultFinishTime>17:00:00</DefaultFinishTime>
  <MinutesPerDay>480</MinutesPerDay><MinutesPerWeek>2400</MinutesPerWeek><DaysPerMonth>20</DaysPerMonth>
  <DefaultTaskType>0</DefaultTaskType><DurationFormat>7</DurationFormat><NewTasksEstimated>0</NewTasksEstimated><WeekStartDay>1</WeekStartDay><NewTasksAreManual>0</NewTasksAreManual>
  <ExtendedAttributes><ExtendedAttribute><FieldID>188743731</FieldID><FieldName>Text1</FieldName><Alias>Schedule Status</Alias></ExtendedAttribute></ExtendedAttributes>
  <Calendars><Calendar><UID>1</UID><Name>Standard</Name><IsBaseCalendar>1</IsBaseCalendar><BaseCalendarUID>-1</BaseCalendarUID><WeekDays><WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay><WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay><WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay></WeekDays></Calendar></Calendars>
  <Tasks>
    <Task><UID>0</UID><ID>0</ID><Name>584 PRY Marcus WWTP Expansion</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>0</OutlineNumber><OutlineLevel>0</OutlineLevel><Summary>1</Summary><Start>2026-08-02T08:00:00</Start><Finish>2027-06-22T17:00:00</Finish></Task>
    <Task><UID>9001</UID><ID>1</ID><Name>PRECONSTRUCTION / SITE-WIDE</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>1</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-08-03T08:00:00</Start><Finish>2026-09-23T17:00:00</Finish></Task>
    <Task><UID>1</UID><ID>2</ID><Name>★ NTP / Notice to Proceed</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-03T08:00:00</Start><Finish>2026-08-03T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>4</ConstraintType><ConstraintDate>2026-08-03T08:00:00</ConstraintDate><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><Notes>NTP 6/9/2026 (given). Subcontract SC-8864-010 executed 6/24/26; Manhattan P6 (Exhibit F) governs — reconcile dates against P6.</Notes></Task>
    <Task><UID>2</UID><ID>3</ID><Name>Mobilization / site setup / GC crew (60-wk general conditions)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-03T08:00:00</Start><Finish>2026-08-07T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GREEN</Value></ExtendedAttribute><Notes>4 laborers + lead + forklift + truck + sweeper priced for 60-wk duration</Notes><PredecessorLink><PredecessorUID>1</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>3</UID><ID>4</ID><Name>Submittals / MOPs / shop drawings — initial package</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-03T08:00:00</Start><Finish>2026-08-21T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Process pipe P-201…P-404, effluent, storm, transfer piping submittals already in flight</Notes><PredecessorLink><PredecessorUID>1</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>4</UID><ID>5</ID><Name>Silt fence perimeter + stabilized construction entrances</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-06T08:00:00</Start><Finish>2026-08-17T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>10 ft beyond limits of disturbance; weekly maintenance for project duration</Notes><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>14400</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>5</UID><ID>6</ID><Name>GPR + hydro-excavation utility locates (site-wide)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-06T08:00:00</Start><Finish>2026-08-19T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GATE — existing live utilities</Value></ExtendedAttribute><Notes>All excavation is hydro-X per scope; fiber trench crossings need shoring/protection</Notes><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>14400</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>6</UID><ID>7</ID><Name>Re-route process water piping — KEEP TANKS LIVE</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-08-20T08:00:00</Start><Finish>2026-09-02T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GATE — plant must stay operational</Value></ExtendedAttribute><Notes>Scope item 34/35: reroute before demo; plant stays live throughout</Notes><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>7</UID><ID>8</ID><Name>Demolition — storm piping/structures, concrete, Valve Group 6 slab + enclosure R&amp;R</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>1.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-03T08:00:00</Start><Finish>2026-09-23T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Incl. sawcut/silica control; VG6 enclosure reinstalled after mods</Notes><PredecessorLink><PredecessorUID>6</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9002</UID><ID>9</ID><Name>EQUALIZATION TANK SIDE — CREW 1</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>2</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-09-10T08:00:00</Start><Finish>2027-04-26T17:00:00</Finish></Task>
    <Task><UID>8</UID><ID>10</ID><Name>Clear / strip / stockpile topsoil — EQ side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-10T08:00:00</Start><Finish>2026-09-21T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9</UID><ID>11</ID><Name>Mass excavation — EQ tank pad + pump house</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-22T08:00:00</Start><Finish>2026-10-19T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Balanced ±1/2 in; Terracon geotech governs</Notes><PredecessorLink><PredecessorUID>8</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>10</UID><ID>12</ID><Name>Engineered / select fill — EQ pad (to 5 ft outside perimeter)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-06T08:00:00</Start><Finish>2026-10-26T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Bottom-of-excavation survey documentation required</Notes><PredecessorLink><PredecessorUID>9</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>11</UID><ID>13</ID><Name>★ EQ tank pad ready for tank contractor</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-27T08:00:00</Start><Finish>2026-10-27T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>12</UID><ID>14</ID><Name>EQ tank erection window — BY OTHERS (BP 40.01)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-27T08:00:00</Start><Finish>2027-03-15T17:00:00</Finish><Duration>PT800H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GATE — tank contractor / P6 window</Value></ExtendedAttribute><Notes>PLUG ~100 wd — pull actual window from Manhattan P6</Notes><PredecessorLink><PredecessorUID>11</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>13</UID><ID>15</ID><Name>Yard piping — EQ side: DI wastewater + storm sewer + structures (~250 LF 8&quot;, 12&quot;/24&quot; runs, 18&quot; RCP)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-24T08:00:00</Start><Finish>2027-01-04T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Runs during tank window; hydro-X, Class C soils, trench boxes</Notes><PredecessorLink><PredecessorUID>12</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>96000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>14</UID><ID>16</ID><Name>Process piping tie-ins — EQ tank (16&quot; connector + P-lines)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-16T08:00:00</Start><Finish>2027-04-12T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Tie-ins after tank set; stub-up for mechanical</Notes><PredecessorLink><PredecessorUID>12</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>15</UID><ID>17</ID><Name>Backfill / return to grade / gravel access road — EQ side (10 ft around tank)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>2.8</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-04-13T08:00:00</Start><Finish>2027-04-26T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9003</UID><ID>18</ID><Name>24-HR HOLDING TANK SIDE — CREW 2</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>3</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2026-09-10T08:00:00</Start><Finish>2027-04-26T17:00:00</Finish></Task>
    <Task><UID>16</UID><ID>19</ID><Name>Clear / strip / stockpile topsoil — 24-hr tank side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-10T08:00:00</Start><Finish>2026-09-21T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Crew 2 parallel with EQ crew per subcontract</Notes><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>17</UID><ID>20</ID><Name>Mass excavation — 24-hr holding tank pad</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-09-22T08:00:00</Start><Finish>2026-10-19T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>18</UID><ID>21</ID><Name>Engineered / select fill — 24-hr tank pad</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-06T08:00:00</Start><Finish>2026-10-26T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>17</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>48000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>19</UID><ID>22</ID><Name>★ 24-hr tank pad ready for tank contractor</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-27T08:00:00</Start><Finish>2026-10-27T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>20</UID><ID>23</ID><Name>24-hr tank erection window — BY OTHERS (BP 40.01)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-10-27T08:00:00</Start><Finish>2027-03-15T17:00:00</Finish><Duration>PT800H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GATE — tank contractor / P6 window</Value></ExtendedAttribute><Notes>PLUG ~100 wd — pull actual window from Manhattan P6</Notes><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>21</UID><ID>24</ID><Name>Yard piping — HT side: transfer piping (12&quot; MegaCub) + 8&quot; effluent + storm</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2026-11-24T08:00:00</Start><Finish>2027-01-04T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Per submittals: 12&quot; holding-tank temp transfer, 8&quot; effluent</Notes><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>96000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>22</UID><ID>25</ID><Name>Process piping tie-ins — 24-hr tank</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-16T08:00:00</Start><Finish>2027-04-12T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>23</UID><ID>26</ID><Name>Backfill / return to grade / gravel access road — HT side</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>3.8</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-04-13T08:00:00</Start><Finish>2027-04-26T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>22</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9004</UID><ID>27</ID><Name>COMMISSIONING / CLOSEOUT</Name><Type>1</Type><IsNull>0</IsNull><OutlineNumber>4</OutlineNumber><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Manual>0</Manual><Start>2027-03-16T08:00:00</Start><Finish>2027-06-22T17:00:00</Finish></Task>
    <Task><UID>24</UID><ID>28</ID><Name>Aggregate base + fine-grade subgrade for paving (asphalt BY OTHERS)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.1</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-04-27T08:00:00</Start><Finish>2027-05-17T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Type A aggregate; blue-topped ±1/2 in; asphalt application by others</Notes><PredecessorLink><PredecessorUID>15</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>25</UID><ID>29</ID><Name>Structure lid adjustments + valve tagging / tracer wire / labeling</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.2</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-04-27T08:00:00</Start><Finish>2027-05-03T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>26</UID><ID>30</ID><Name>Site restoration / topsoil / vegetation + erosion-control removal</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.3</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-18T08:00:00</Start><Finish>2027-05-31T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Silt fence removed at completion once vegetation established</Notes><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>27</UID><ID>31</ID><Name>QA/QC testing + documentation (plans 2 wks ahead of testing)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.4</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-03-16T08:00:00</Start><Finish>2027-03-29T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>Per MCC/Client-approved testing plans</Notes><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>22</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>28</UID><ID>32</ID><Name>Commissioning — L1/L2/L3 (+ L4/L5 support)</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.5</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-05-04T08:00:00</Start><Finish>2027-05-24T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>GATE — client commissioning program</Value></ExtendedAttribute><Notes>MARCUS commissioning; third-party issue resolution + retesting support</Notes><PredecessorLink><PredecessorUID>27</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>25</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>29</UID><ID>33</ID><Name>Closeout documentation — MARCUS Deliverables Matrix + as-builts</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.6</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-06-01T08:00:00</Start><Finish>2027-06-14T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>0</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>PRELIM — estimate</Value></ExtendedAttribute><Notes>As-built survey of contours/finish grades to Manhattan</Notes><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>28</PredecessorUID><Type>3</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>30</UID><ID>34</ID><Name>★ SUBSTANTIAL COMPLETION</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.7</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-06-15T08:00:00</Start><Finish>2027-06-15T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>28</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>29</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>31</UID><ID>35</ID><Name>★ FINAL COMPLETION / DEMOB</Name><Type>0</Type><IsNull>0</IsNull><OutlineNumber>4.8</OutlineNumber><OutlineLevel>2</OutlineLevel><Priority>500</Priority><Manual>0</Manual><Start>2027-06-22T08:00:00</Start><Finish>2027-06-22T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><Milestone>1</Milestone><Summary>0</Summary><Critical>0</Critical><Estimated>0</Estimated><ConstraintType>0</ConstraintType><ExtendedAttribute><FieldID>188743731</FieldID><Value>MILESTONE</Value></ExtendedAttribute><PredecessorLink><PredecessorUID>30</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>24000</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
  </Tasks>