Tahlequah Municipal Airport (TQH) ยท CSPP Schedule

Apron Rehab + Taxilane/AWOS (concurrent) ยท FAA AC 150/5370-2G ยท read-only view
NTP: 7/27/26 Apron 65 CD due: 9/30/26 Taxilane 80 CD due: 10/15/26 Forecast Substantial Completion: 9/23/26
WBSActivity / TaskPhase StartFinishJulAugSep
7/137/207/278/38/108/178/248/319/79/149/21
PRECONSTRUCTION & SUBMITTALS โ€” before / at NTP
PC.1โ˜…CQCP (C-100) + SPCD submittals โ€” approval
Submit for engineer (Lochner) approval prior to work
Pre7/13/267/24/26
PC.2Project survey & stakeout (X-202)
Both contracts
Pre7/13/267/14/26
PC.3โ˜…NAVAID / AWOS outage coordination โ€” FAA Tech Ops (ยง3.9)
45-day advance notice โ€” governs AWOS removal
Pre7/13/267/13/26
CONTRACT A โ€” APRON REHAB (Base Bid โ‰ค65 CD) โ€” MOBILIZATION
1.1โ˜…Mobilization / contractor staging (C-105)
NTP = Mon 07/27/26
A7/27/267/29/26
1.2Temp marking, lighting & barricades (TEMP) + erosion control (C-102)A7/27/267/28/26
PHASE 1 โ€” TAXIWAY OFA + SOUTH APRON โ—€ open taxiway & fueling first
1.3โ˜…Cold milling โ€” south / OFA (part of 11,725 SY)
P-101; mill failed asphalt
A7/29/267/31/26
1.4Asphalt patch / wedge repair โ€” south (P-101)A8/3/268/4/26
1.5Edge grading (P-152)A8/5/268/5/26
1.6Tack coat + paving fabric interlayer โ€” south (P-603)A8/6/268/7/26
1.7โ˜…Asphalt overlay 3"/3.5" โ€” south (P-405)A8/10/268/12/26
1.8Pavement markings โ€” south (P-620)A8/13/268/14/26
1.9Install tie-down anchors (33 EA)A8/10/268/11/26
M1โ˜…โ˜… OPEN taxiway + fueling apron (Phase 1)
Fueling apron & taxiway required open within Phase 1
A8/14/26โ€”โ—†
PHASE 2 โ€” NORTH APRON (contractor option: concurrent)
2.1Cold milling โ€” north (P-101)
May run concurrent w/ south
A8/10/268/12/26
2.2Tack + paving fabric โ€” northA8/13/268/14/26
2.3โ˜…Asphalt overlay 3"/3.5" โ€” north (P-405)A8/17/268/19/26
2.4Pavement markings โ€” north (P-620)A8/20/268/21/26
2.5Sodding (1,055 SY, T-904) + cleanupA8/20/268/21/26
M2โ˜…โ˜… APRON SUBSTANTIAL COMPLETION (โ‰ค65 CD)
Base Bid contract complete
A8/21/26โ€”โ—†
CONTRACT A โ€” ADD ALT No.1 ยท RSA GRADING (โ‰ค15 CD) โ€” 2 areas
AA.0Temp marking / erosion control (TEMP / C-102)
After taxiway opens
AA18/17/268/17/26
AA.1Modify manhole (P-101)AA18/18/268/19/26
AA.2โ˜…Earthwork / RSA grading โ€” Rwy 17 โš‘ ROCK excavation (P-152)
Rock excavation known in Rwy 17 grading limits
AA18/20/268/26/26
AA.3Seeding (3 AC, T-901) + mulching (3 AC, T-908)AA18/27/268/28/26
M3โ˜…โ˜… RSA GRADING COMPLETE (โ‰ค15 CD)AA18/31/26โ€”โ—†
CONTRACT B โ€” TAXILANE & RELOCATE AWOS (Base Bid โ‰ค80 CD) โ€” MOBILIZATION
B1.1โ˜…Mobilization (C-105) + CQCP (C-100)
Concurrent with Contract A
B7/27/267/29/26
B1.2Temp marking/lighting/barricades + erosion + temp seeding (C-102)B7/27/267/28/26
B1.3Remove existing lighting system (P-101)B7/29/267/30/26
B1.4โ˜…Remove existing AWOS system (P-101)
Requires FAA outage window (PC.3)
B7/31/268/3/26
CONTRACT B โ€” EARTHWORK & DRAINAGE
B2.1Saw cut (365 LF) + pavement removal (30 SY, P-101)B7/31/268/3/26
B2.2โ˜…Unclassified excavation (1,110 CY, P-152)B8/4/268/7/26
B2.3Unsuitable subgrade removal & replacement (115 CY)B8/10/268/11/26
B2.4โ˜…Underdrain 6" (630 LF) + outlet pipe (150 LF) + cleanouts (D-705)B8/12/268/17/26
B2.5Splash pads (2 EA, D-705)B8/18/268/18/26
CONTRACT B โ€” PAVING
B3.1โ˜…8" subbase + 6" aggregate base (2,550 SY, ODOT-303)B8/18/268/20/26
B3.2Prime coat (845 GAL, P-602)B8/21/268/21/26
B3.3โ˜…Asphalt surface course 4" S4 (680 TON, ODOT-411) + tackB8/24/268/25/26
CONTRACT B โ€” ELECTRICAL & AWOS
B4.12" PVC duct + concrete-encased duct (621 LF, L-110)
Concurrent w/ drainage
B8/10/268/12/26
B4.2L-824 5kV cable (980 LF) + counterpoise (360 LF, L-108)B8/13/268/17/26
B4.3Junction boxes L-867 (2) + cover plate (L-115)B8/18/268/18/26
B4.4โ˜…Taxiway edge lights L-861T (14 EA) + bases (L-125)
After paving
B8/26/268/28/26
B4.5โ˜…Furnish & install new AWOS + commissioning
Long-lead; coordinate FAA flight check
B8/4/268/11/26
CONTRACT B โ€” CLOSEOUT
B5.1Pavement markings โ€” reflectorized + non-refl (P-620)B8/31/269/1/26
B5.2Seeding (2 AC) + sodding (1,750 SY) + mulching (2 AC)B8/24/268/25/26
M4โ˜…โ˜… TAXILANE SUBSTANTIAL COMPLETION (โ‰ค80 CD)B9/1/26โ€”โ—†
PROJECT CLOSEOUT
CL.1โ˜…Grass establishment / final acceptance
~3 cal wks establishment per engineer
โ€”9/2/269/22/26
CL.2โ˜…โ˜… FINAL ACCEPTANCE โ€” both contractsโ€”9/23/26โ€”โ—†
Earthwork / grading / aggregate / subbaseTemp marking, barricades, closed-areaAdd Alt No.1 โ€” RSA gradingAsphalt paving (mill / overlay / surface)Structures & drainageElectrical / lighting / pavement markingsOPEN / reopen milestoneSubstantial completion / final acceptanceFAA compliance / coordinationโ—†Milestone
Generated 7/1/26 from the CSPP activity model โ€” same source as the Excel model and MS Project file, so it stays in sync. Durations are working days; contract caps are calendar days. Planning-rate durations โ€” verify against the crew plan before relying on dates.