Methodology — Earned Value Method
% Complete & Earned Value% Complete = Actual Cost ÷ Est. Final Cost. Earned Value = Revised Contract × % Complete.
Over / (Under) BilledBilled to Date − Earned Value. Positive = collected ahead of work. Negative = cash exposure.
Phase VarianceActual − Budget per phase code. Unbudgeted (.888/.999) = cost with no estimate loaded.
Health Code Phases.888 = CO/write-off (pay-app quantity overrun) · .999 = negotiate & bill (T&M extra work) · .777 = claim capture (unique billing). See Job Health Codes tab.